- G59 Testing
- Update 7th March
- Update 27th February 2018
- Update 19th February
- Update 19th February
- The Railway Underpass
- SSE working on the transformer in January 2018
- SSE working on overhead cables
- Signing the lease – Duncan MacLachlan, Arrochar & Tarbet Communit Trust, Sir Malocon and Lady Katherine Colquhorn, and David MacCowan the Chairman of Luss and Arden Community Development Trust
- Update 4th November -Turbine Base
- Duncan MacLachlan, Arrochar & Tarbet Communit Trust, David MacCowan the Chairman of Luss and Arden Community Development Trust Sir Malocon and Lady Katherine Colquhorn.
- Update (3) 29th October
- Update (2) 29th October
- Update (1) 29th October
- Construction Update (2) 24th October
- Construction Progress 24th October
- Construction Update (2) 16/10/17
- Construction Update (1) 16/10/17
- Jamie Wallace of Highland Eco Design showing the schoolchildren a model Turbine and Generator.
- Construction Update 29/09/17
- Construction Work 19/09/17
- The Cobbler Mountain
- Loch and mountain
- Powerhouse
- View of Loch